Home CANADA New Brunswick’s Point Lepreau nuclear power plant down until mid-November

New Brunswick’s Point Lepreau nuclear power plant down until mid-November

by admin

CITYnews halifax / By The Canadian Press

SAINT JOHN, N.B. — New Brunswick’s electrical utility says its sole nuclear generating station will remain shut down until at least mid-November.

The station at Point Lepreau, N.B., has been off-line since April 6, while NB Power carried out a planned 100-day maintenance outage.

In a news release Thursday, the utility said that during startup a “critical issue” related to the 660-megawatt power plant’s main generator was identified and needs to be addressed before the station can return to service.

NB Power has not specified what the problem is, saying only that the “full extent of this issue is still being investigated and we are working toward resolving it.”

Dominique Couture, a spokeswoman for the utility, said in an email Friday that teams at the plant were conducting a detailed forensic analysis on the generator to determine the cause of the problem.

“We are testing the generator stator bars to better understand the nature of the issue and its impact on their condition,” said Couture. Stator bars are part of the rotary system in electric generators.

“There is no risk to the safety of our employees, the public or the environment, and we are conducting this work following rigorous safety protocols,” she said.

The utility said the outage won’t affect the supply of power to its customers, with electricity being provided from its other generating stations and utilities in neighbouring areas.

Generating stations at Coleson Cove, N.B., and Bayside, N.B., are fully operational, while the station at Belledune, N.B., is off-line for planned maintenance to ensure its reliability during colder months, Couture said.

“Final outage costs will not be determined until the station is back online and are affected by variations in replacement power costs,” she said.

NB Power has cautioned that while new developments can affect its schedule, it is working “toward a goal” of restoring the nuclear plant’s operations by mid-November.

The Point Lepreau facility is the only nuclear power plant in Atlantic Canada.

This report by The Canadian Press was first published Aug. 16, 2024.

The Canadian Press

You may also like

Editor-in-Chief: Nabil El-bkaili

CANADAVOICE is a free website  officially registered in NS / Canada.

 We are talking about CANADA'S international relations and their repercussions on

peace in the world.

 We care about matters related to asylum ,  refugees , immigration and their role in the development of CANADA.

We care about the economic and Culture movement and living in CANADA and the economic activity and its development in NOVA  SCOTIA and all Canadian provinces.

 CANADA VOICE is THE VOICE OF CANADA to the world

Published By : 4381689 CANADA VOICE EPUBLISHING NEWS - MEDIA WEBSITE

Tegistry id 438173 NS-HALIFAX

1013-5565 Nora Bernard str B3K 5K9  NS - Halifax  Canada

1 902 2217137 –

Email: nelbkaili@yahoo.com 

 

TOP NEWS

الإعلام الإسرائيلي يكشف ملامح صفقة الأسرى والهدنة

by admin

توصية أميركية بحصول كبار السن على جرعة أخرى من لقاحات كورونا

by admin

اتفاق محتمل للأطراف الليبية يهدد مصير حكومة الدبيبة

by admin

زاو ووكي فنان التجليات البصرية الروحية

by admin

لماذا لا تدرّس الجامعات العربية علم الجمال؟

by admin

حملة لـ”كسر الصمت” حيال التحرش داخل أماكن العمل في الأردن

by admin

الجراحة الروبوتية ثورة في عالم الطب تبشر ببزوغ عصر جديد

by admin

عودة ثنائية “دي بروين – هالاند” الأكثر رعبا في أوروبا

by admin

زيدان على رأس أهداف مالك مانشستر يونايتد الجديد لخلافة تن هاغ

by admin

Retour du visa pour les visiteurs mexicains au Canada

by admin
Facebook Twitter Youtube
Editor-in-Chief : Nabil El-bkaili