CANADAHALIFAX news Another N.S. Power hydro dam project is in serious trouble by admin 16 فبراير، 2022 written by admin 16 فبراير، 2022 173 Tusket dam refurbishment already 3 years late and $18M over budget Paul Withers · CBC News Provincial regulators have given Nova Scotia Power until next week to explain the latest setback of the company’s ill-fated refurbishment of the Tusket hydro dam near Yarmouth, N.S. Nova Scotia Power is halting work yet again as water continues to seep into the construction zone despite multiple attempts to seal off the site. The utility told regulators it intends to stop construction and stabilize the area “in order to finalize a modified construction plan and further assess the cost and schedule impacts to the project.” The refurbishment is already three years behind schedule and $18 million over budget. Nova Scotia Power wants ratepayers to pick up the cost. “Despite the progress made to date, water migration remains an ongoing issue,” the company told the Nova Scotia Utility and Review Board (UARB) in its most recent update on Jan. 31. Last summer, Nova Scotia Power applied to the provincial regulator for “authorization to overspend” on the Tusket dam — regulatory speak for sticking ratepayers with the bill. Costs have doubled since construction began in 2017. Not clear when project will be completed But the bottom line is not clear, nor is the completion date for the project. The most recent estimate put the final cost at $36 million with work ending in February 2023. “Further work is required before N.S. Power can confirm its updated construction plan and authorization to overspend … amount, which may necessitate amendments to the application. The company is not in a position at this time to provide a timeline as to when that work will be completed,” Nova Scotia Power told regulators. The UARB is demanding answers from the utility no later than Feb. 23, including an explanation of the further work that’s required. Nova Scotia Power’s request to charge ratepayers $18 million in overspending includes $3.2 million in “contingency funding.” Nova Scotia Power declines comment The UARB has ordered the company to report next week on additional contingency spending from Oct. 1, 2021, to Dec. 31, 2021. Nova Scotia Power has also been told to produce quarterly reports on contingency spending. The regulator granted Nova Scotia Power’s request to suspend proceedings to recover its overspending from ratepayers in December shortly after the company first disclosed its efforts to halt water infiltration had failed. Nova Scotia Power declined to comment citing the ongoing regulatory review. Gaspereau Lake dam Meanwhile, the utility has halted work at another dam project, but for different reasons. Refurbishment of the Gaspereau Lake dam was stopped after Mi’kmaw leaders withdrew support for the project. The dam is the site of a large, Indigenous archeological find which has so far delayed the refurbishment by 14 years and pushed the cost up by 421 per cent to $22 million. Nova Scotia Power also wants customers to pay for the overspending. 142 comments 0 FacebookTwitterPinterestEmail admin previous post Rain, wind and a flash-freeze forecasted for Halifax next post RCMP accused of using ammunition charge to deflect from N.S. mass shooting failures You may also like Premier Tim Houston reverses some budget cuts amid... 11 مارس، 2026 Budget cuts put seniors and vulnerable Nova Scotians... 11 مارس، 2026 Police charge pair linked to several robberies in... 11 مارس، 2026 Serial killer Allan Legere, New Brunswick’s ‘Monster of... 11 مارس، 2026 أكثر من 7.000 كندي غادروا الشرق الأوسط منذ... 11 مارس، 2026 كارني يؤكّد أنّ كندا ’’لن تشارك أبداً‘‘ في... 11 مارس، 2026 فورد يُدين بشدة إطلاق النار على القنصلية الأميركية... 11 مارس، 2026 كندا تعطي ’’تيك توك‘‘ موافقة مشروطة لمواصلة العمل 11 مارس، 2026 كارني وحمد بن ثاني يناقشان ’’خفض التصعيد‘‘ في... 11 مارس، 2026 Gas prices to change as energy board invokes... 10 مارس، 2026 Leave a Comment Save my name, email, and website in this browser for the next time I comment. Δ